The country’s electricity transmission
grid is under threat as a result of the vandalism of a tower in Delta
State, which has led to a fall in power generation by 480 megawatts, the
Transmission Company of Nigeria has said.
According to the TCN, the fall in
electricity generation is due to the vandalism of tower No. 62 along the
Okpai-Onitsha 330kV double circuit transmission line, which evacuates
power from the Okpai Power Station in Delta State.
Power generation in the country had hit
an all-time high of 4,810.7MW on August 25 this year after hovering
around 3,500MW for about a year. This is despite the fact that the
electricity generation and distribution arms of the sector had been run
by private entities all this while.
Findings from the
Federal Ministry of Power on Monday showed that the actual energy sent
out as of November 15 was 3,682.32MW, while energy generation was put at
3,754.96MW.
The transmission company, in a statement
by its management, said the incident involving the vandalised tower
took place at Asaba Uchi, Ndokwa East Local Government Area of Delta
State, adding that this “has resulted in the reduction of available
power to the national grid by about 480MW.”
It added, “At about 4:51am on Tuesday,
November 10, 2015, the Okpai-Onitsha 330kV transmission line tripped and
the cause of the tripping was traced to tower No. 62, which had been
vandalised.
“Two of the four legs of the
transmission tower were cut by vandals, causing the tower to hang
precariously. This poses a major threat to the transmission grid
integrity as a total collapse of this tower could bring down several
other towers along the transmission line route.”
The firm stated that its engineering
crew inspected the site of the incident the same day and had already
mobilised a reputable engineering contracting firm to anchor the
transmission tower temporarily in order to avoid a total collapse.
“Anchoring the vandalised tower will
enable the TCN to energise one of the circuits on the tower to enable it
recommence partial power evacuation from the Okapi Power Station to the
national grid. This is expected to be achieved within a fortnight,” the
TCN stated.
The statement further noted that the
company would construct a new tower to replace the vandalised one, but
that due to the swampy nature of the site, construction could only
commence in the dry season when vehicular access would be possible.
The TCN said it would continue to work
towards a robust transmission grid and pleaded with the host communities
to work with the company in its fight against the activities of
vandals.
The firm said the construction of a new
tower would cost millions of naira that would otherwise have been
applied to its grid expansion plans.
No comments:
Post a Comment